Construction Update December 1, 2008

November 15, 2008 photos of Gruv site.

Construction Update November 19, 2008

October 24, 2008 photos of Gruv site.

Construction Update October 22, 2008

October 1, 2008 photos of Gruv site.

Construction Update October 2, 2008

September 19, 2008 photos of Gruv site.

Construction Update October 2, 2008

September 12, 2008 photos of Gruv site.

Construction Update September 5, 2008

September 5, 2008 photos of Gruv site.

Construction Update August 29, 2008

August 12, 2008 photos of Gruv site.

Construction Update August 1, 2008

August 1, 2008 photos of Gruv site.

Construction Update July 15, 2008

July 15, 2008 photos of Gruv site.

Construction Update July 8, 2008

As of July 7, 2008 concreting of perimeter underground parkade walls was completed from grid 1 to 13 while work continued on the perimeter walls and supporting columns from grid 13 to 33. During the second week of June all underground plumbing services were installed and concrete was placed in the parkade raft slab from grid 33 to 50. Formwork and re-enforcing steel was completed on the perimeter walls and supporting columns from grid 13 to 33 and concreting was also substantially complete.

Construction Update June 10, 2008

June 10, 2008 photos of Gruv site.

Construction Update June 2, 2008

As shown on photos taken on June 2, 2008, concreting of elevator pit was substantially complete. Erection of forms for the parkade walls from Grid 1 to 13 was completed on all three sides along with some of the supporting columns. Perimeter drain tile in this area was also substantially complete.

Construction Update May 23, 2008

During 3rd week of May all underground plumbing pipes from Grid line 1 to 33 were installed and raft slab concrete was completed from Grid line 1 to 13 as shown on photos taken on May 23, 2008. By the end of May the bulk excavation of underground parkade was substantially complete. Stabilization of vertical cuts along east and south property line was substantially complete including shotcrete, drilling and grouting of anchor bolts.

Construction Update May 13, 2008

Mass excavation for the underground parkade commenced during the last week of April 2008. Excavation was concentrated starting from west property line from Grid line 1 to 13 and continued to east property line towards King George Highway. This excavated section was backfilled with imported granular material and compacted. As the excavation progressed beyond Grid line 13, area from Grid 1 to 13 was prepared for raft slab and the vertical cut along King George Hwy was prepared for shotcrete and anchor bolts (as sown on photos taken on May 13, 2008).